Investor Presentation
Released
Released
Announcement PDF
SCALING UP
FOR SUCCESS
THE TALLEBUNG TIN PROJECT, NSW
A LARGE AND GROWING RESOURCE, SET TO BENEFIT FROM CUTTING-EDGE
TECHNOLOGY, EFFICIENT DEVELOPENT AND GROWING TIN DEMAND
INVESTOR PRESENTATION | NOVEMBER 2025 | OLIVER DAVIES, MANAGING DIRECTOR AND CEO
ASX: SKY
Disclaimer
Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause actual results to be materially different from those expressed or implied by such forward looking information, including risks associated with investments in private
and publicly listed companies such as the Company; risks associated with general economic conditions; the risk that further funding may be required but unavailable for the ongoing development of the Company’s projects or future acquisitions; changes in government
regulations, policies or legislation; unforeseen expenses; fluctuations in commodity prices; fluctuation in exchange rates; litigation risk; restrictions on the repatriation of earnings by the Company’s subsidiaries; the inherent risks and dangers of mining exploration and operations
in general; risk of continued negative operating cashflow; the possibility that required permits may not be obtained; environmental risks; uncertainty in the estimation of mineral resources and mineral reserves; general risks associated with the feasibility and development of each
of the Company’s projects; foreign investment risks in Australia; changes in laws or regulations; future actions by government; breach of any of the contracts through which the Company holds property rights; defects in or challenges to the Company’s property interests;
uninsured hazards; disruptions to the Company’s supplies or service providers; reliance on key personnel and retention of key employees.
Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management of the Company made in light of their experience and their perception of trends, current conditions and expected developments, as well as other factors that
management believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. The Company believes that the assumptions and expectations reflected in such forward-looking information are
reasonable.
Assumptions have been made regarding, among other things: the Company’s ability to carry on its future exploration, development and production activities, the timely receipt of required approvals, the price of tin, gold, copper and base metals, the ability of the Company to
operate in a safe, efficient and effective manner and the ability of the Company to obtain financing as and when required and on reasonable terms. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Although
the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no
assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not
undertake to update any forward-looking information, except in accordance with applicable securities laws.
No Liability/Summary Information
The Company has prepared the Presentation Materials based on information available to it at the time of preparation. No representation or warranty, express or implied, is made as to the fairness, accuracy or completeness of the information, opinions and conclusions contained
in the Presentation Materials. To the maximum extent permitted by law, the Company, its related bodies corporate (as that term is defined in the Corporations Act 2001 (Commonwealth of Australia)) and the officers, directors, employees, advisers and agents of those entities do
not accept any responsibility or liability including, without limitation, any liability arising from fault or negligence on the part of any person, for any loss arising from the use of the Presentation Materials or its contents or otherwise arising in connection with it. Post 1989,
exploration results detailed in this presentation have previously been reported to the ASX or in the independent geologist report contained in the Prospectus lodged on 18 April 2019. Endowment = current resource plus production. Coordinate system on maps is MGA94 Zone55
unless otherwise stated.
Competent Persons Statement
The information in this report that relates to Exploration Results and the Doradilla Exploration Target is based on information compiled by Mr. Oliver Davies, who is a Member of the Australasian Institute of Geoscientists. Mr. Oliver Davies is an employee of Sky Metals Ltd and has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves.’ Mr. Davies consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
The information in this report that relates to the Tallebung Mineral Resource Estimate and Exploration Target was prepared by Luke Burlet, who is a Member and Chartered Professional (Geology) of the Australasian Institute of Geoscientists. Luke Burlet is a Director of H & S
Consultants and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves.’ Mr. Burlet consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
Cautionary Statement regarding Exploration Targets
An Exploration Target of 23 – 32 Mt @ 0.14 – 0.17% Tin has been previously reported for the Tallebung Tin Project and 10 – 15 Mt @ 0.32-0.42% Tin for the Doradilla Project (please see SKY ASX Announcement 23 January 2024 and SKY ASX Announcement 14 July 2025,
respectively, for details). The potential quantity and grade referred to in this presentation as Exploration Targets are conceptual in nature, as there has been insufficient exploration to estimate a Mineral Resource and it is uncertain if further exploration will result in the estimation
of a Mineral Resource. SKY will continue drilling of these exploration targets in the coming months with the aim to expand the MRE and grow confidence in this estimated Exploration Targets. Supporting report and further details on the Mineral Resource Estimate and the
definition of the Exploration Target are included in SKY ASX Announcement 23 January 2024 and SKY ASX Announcement 14 July 2025.
2
ASX: SKY
DISCLAIMER – IMPORTANT INFORMATION
ASX: SKY
3
SKY INVESTMENT SNAPSHOT
CREATING A NEW AUSTRALIAN TIN PRODUCER
ASX: SKY
TALLEBUNG
SYDNEY
DORADILLA
CORNERSTONE ASSET
Flagship Tallebung Tin Project in NSW -
brownfields asset with substantial JORC
Resource & compelling upside
QUALITY TEAM
Highly regarded board & leadership
team with exceptional track record,
led by Norm Seckold and Oliver Davies
TIN MARKET
Compelling market outlook for tin,
driven by its irreplaceable use in modern
technologies and supply constraints
ASSET PIPELINE
Building a strong pipeline of emerging
development assets that now includes
the Doradilla Tin Project
VALUE
Compelling value proposition with a
market capitalisation of just ~$60
million, strongly leveraged to growth
NEAR-TERM GROWTH
Second 15,000m drill program ongoing to
further target resource growth & upgrades –
taking the existing deposit to the next level
EXPERIENCED AND PROVEN MANAGEMENT
NORMAN SECKOLD | CHAIRMAN
30+ years in the full-time management of natural
resource companies. Past Chairman and Director of
listed companies including Bolnisi Gold NL, Timberline
Minerals Inc., Perseverance Corporation Ltd, Valdora
Minerals NL, Palmarejo Silver and Gold Corp, Kings
Minerals NL, Mogul Mining NL, and Santana Minerals
Ltd. Currently Chairman Nickel Industries Ltd, Alpha HPA
Ltd and Fulcrum Lithium Ltd and Director of Uvre Ltd.
OLIVER DAVIES | MANAGING DIRECTOR
At SKY since listing in 2019. Previously in exploration and
operational roles with Evolution Mining and Alkane
Resources in NSW and Qld. Mr. Davies has worked closely
on several successful NSW discoveries including Evolution
Mining’s significant expansion at the Lake Cowal Gold Mine
and Alkane’s exploration success with the discoveries at
Tomingley and Boda.
RIMAS KAIRAITIS | NON-EXECUTIVE DIRECTOR
25+ years experience in minerals exploration and resource
development in gold, base metals and industrial minerals.
Mr. Kairaitis was founding Managing Director and CEO of
Aurelia Metals, which he steered from a junior exploration
company to a profitable NSW based gold and base metals
producer. Mr. Kairaitis is also the founding Managing
Director and current Executive Director of Alpha HPA Ltd.
RICHARD HILL | NON-EXECUTIVE DIRECTOR
25+ years experience in the mineral resources sector as a
geologist and solicitor. Mr. Hill has a successful track record
of guiding ASX listed mining companies from the exploration
and discovery phase through to development in a range of
commodities. These have included past roles as founding
Director for Aurelia Metals Ltd and as former Chairman of
New World Resources Ltd and Genesis Minerals Ltd as well
as current Chairman of Accelerate Resources Ltd.
Shares on issue
Options & Performance Rights
Share price (20 November)
Market capitalisation
Cash (30 Sept 2025)
+ Capital Raise (Board contribution
after shareholder approval)
Debt
CAPITAL STRUCTURE
824.7M
44.2M
~$0.078
~$64.3M
~$6.02M
+$0.59M
Nil
SHAREHOLDERS
Top 20 holders
Board and Management
48.2%
11.8%
EXPERT GUIDANCE | SKY’s CONSULTANTS
Tallebung Environmental Mining Approvals: R.W. Corkery & Co. to expediate and advise on best practice for environmental studies and mining approvals process.
Tallebung Metallurgy – Gunn Metallurgy, TOMRA Ore Sorting Solutions, ALS Burnie and ALS Perth engaged to conduct metallurgical testwork.
Tallebung Resource Estimation – H&SC modelled and estimated the MRE and Exploration Target.
4
ASX: SKY
TIN – IRREPLACEABLE IN MODERN TECHNOLOGIES
ASX: SKY 5
The conductive glue in every
circuit – tin solder physically
connects every component in
a circuit board. Used in laptops,
TVs, cars and headphones.
The invisible ingredient
for strength – tin oxide
coatings create stronger-
scratch resistant glass
The gold standard for
food preservation – tin is
corrosion resistant and
non-toxic
Powering the future of
mobility – critical for the
next generation of EV
battery anodes.
• Fundamental
structural demand
growth – triggering
a supply crunch
after 30+ years of
under-investment
• Tin is vital for EVs,
Renewable Energy,
AI and all
electronics
• New solar PV tech
increases tin use
• – tin replacing lead
and indium in new
PSC solar cells
Source: BNEF, Rho Motion, Macquarie Strategy – April 2024
Increase
in
tin
demand
Tin
Price
ASX: SKY
TIN PRICE
– INCREASING WITH GLOBAL DEMAND
6
TIN: ESSENTIAL ELECTRIFICATION METAL
– GLOBAL SUPPLY DISRUPTIONS
• Inelastic tin price – strong demand
underpinned by tin’s irreplaceable role in
electronics, increasing demand with AI and EVs
• Over 5% of world tin production out when
Alphamin’s Bisie tin mine shut in DRC
• Heavily disrupted Indonesian tin production
decreased by 33% in 2024 – previously
Indonesia accounted for 20% of global tin
supply
• Limited reliable and ethical sources
• Few tin investment opportunities on ASX
2021 GLOBAL TIN SUPPLY
BY COUNTRY (TPA)
S o u r c e : I T A S o u r c e : I T A
7
ASX: SKY
• Tin discovered in the 1890s and mined into the mid-
1980s
• Small shafts and open pits mined hard rock tin veins,
culminating in large scale alluvial mining production
in the 1960s-70s
• Infrastructure already in place from previous mining
includes:
- Powerlines to site
- Excellent road access
• Hard-rock tin source remains intact and largely
unmined
• Large-scale tin deposit now defined over 2km and
still growing with every hole
Tallebung Tin Mine – Aerial Image of Historic Mining and Infrastructure.
8
MAJOR HISTORIC OPERATION
TALLEBUNG TIN PROJECT
ASX: SKY
• Low-Cost Mining Proposition – Shallow
deposit at surface, very low strip ratio and
growing with every new drill-hole
• Exceptional Upgrade – Ore sorting ideally
suited to the deposit – increases grade >10x,
removing over 90% of mined mass in high tin
recovery bulk testwork
• Low-Cost Processing – Simple gravity circuit
for a saleable tin concentrate
• High Payability on Tin Concentrate – over 90%
payability on a +60% tin concentrate, with
sample tin concentrate from bulk sample
metallurgical program available shortly
Tallebung Tin Mine – Drone Photo looking East down the Central Lead Open Pit.
TALLEBUNG TIN PROJECT
KEY COMPETITIVE ADVANTAGES
9
ASX: SKY
• New intercepts show potential for shallow, higher-grade tin
and silver outside the existing MRE
• Three main shallow target areas for Resource growth:
• Southern extensions where TBRC078 intercepted:
11m @ 1.02% Sn & 77.9g/t Ag from 64m
• New south-eastern silver discovery in TBRC171:
3m @ 686.3g/t Ag & 0.96% Sn from 24m
• Eastern extensions in TBRC090 which intercepted:
10m @ 0.69% Sn & 23.7g/t Ag from 23m
• Results demonstrate that the deposit remains open in all
directions – latest drilling program has extended these zones
and identified new shallow, high-grade mineralisation
• Successful RC program substantially expanding the existing
MRE size, confidence and grade with more results to be
release over the coming months as drilling continues
EVOLVING HIGH-GRADE TIN-SILVER
DISCOVERIES AND EXTENSIONS
10
ASX: SKY
GROWING LARGE HARDROCK TIN RESOURCE
Schematic Plan View - Tallebung Tin Mine - Highlight drill intercepts and TOMRA ore sorting results.
• Recent higher-grade expansion not included in the
MRE or Exploration Target estimates
• Jan 2024 MRE, Inferred and Indicated, totalling:
15.6 Mt @ 0.15% Tin for 23kt of contained Tin1
• Exploration Target estimated concurrently:
23 – 32 Mt @ 0.14 – 0.17% Tin1,2
• Tin mineralisation highly amenable to 10x upgrade
using TOMRA Ore Sorting – 0.15% = +1.50% Tin
1For further details on the MRE and Exploration Target please see SKY ASX Announcement 23 January 2024 and Appendix 1.
2Please see the Cautionary Statement regarding Exploration Targets in the Disclaimer on Slide 2 and Appendix 1.
11
ASX: SKY
Schematic Cross-Section of existing Shallow High-Grade Zone
• Tallebung tin deposit is ideally matched to ore sorting
technology
• Conservative, Stage 1 bulk TOMRA Ore Sorting
testwork demonstrated increases in grade of +1000%
and rejects +90% of mass
• Resource grade increases from 0.15% Tin x 10 =
to over 1.50% Tin with 95% tin recovery
• Reduced mass means smaller, lower plant costs to
produce a saleable tin concentrate
• Bulk sample of over 75t of mineralisation was
excavated, crushed and ore sorted on a full-scale
TOMRA ore sorter to optimise process, culmination
of over 3 years of testwork
Accepted
Rejected
Schematic of a TOMRA
XRT Ore Sorter
Cassiterite from Tallebung –
Scale in mm
Dense tin – cassiterite “nuggets”
detected by ore sorter and accepted
Host rock and quartz vein without
tin rejected by ore sorter
The image of cassiterite from Tallebung is intended for illustrative purposes only and SKY does not
intend to assay this sample.
TOMRA-HIGH TECHNOLOGY CHANGES THE GAME
12
ASX: SKY
• Extremely effective sorting of Tallebung Tin
achieved as Tin is ideally present as large,
discrete ‘chunks’, easily classified by the
TOMRA XRT ore sorter
• 75t bulk sample testwork on full-scale ore
sorters demonstrate:
– Stage 1 Sorting: Tin upgraded from 0.17%
Sn to 2.32% Sn (a 13x increase)
with +94.8% Sn recovery in total.
– Stage 2 Sorting: Further upgrade to 10.8%
Sn (a further 4.6x increase on Stage 1)
with a +70% Sn recovery.
• Over 90% mass reduction significantly
reduces any future project CAPEX and
OPEX
TOMRA-HIGH TECHNOLOGY CHANGES THE GAME
13
ASX: SKY
TOMRA-HIGH TECHNOLOGY CHANGES THE GAME
14
ASX: SKY
• Groundwater Monitoring Bores – 2 years required
monitoring now completed
• Geochemical Characterisation – Initial deposit
characterisation completed, weathering only variable
• Weather Station – Installed over 1 year ago and now
collected data needed
• Biodiversity Study – Initial background study completed
with seasonal and detailed studies progressing
• Environmental Program waiting on precise mining
plans in coming months for final works
• Pilot-scale plant testwork providing crucial data to:
• Optimising the metallurgical flowsheet,
• Produce tin concentrate for end-user marketing,
• Increase confidence in Resource Estimation Trench T5 while being excavated – looking north towards the
edge of the Southern Open Pit with the walls in background
PROGRESSING WORK PROGRAM:
PAVING WAY TO MINING
15
ASX: SKY
Tallebung Weather Station
Goat-proof
fence
Weather station
and mast
• Large-scale, multi-rig drill out
ongoing to expand MRE, increase
resource confidence and grow
higher-grade discoveries with
completion scheduled in the
coming months
• Release updated MRE with
addition of higher-grade
discoveries, in-fill drilling and bulk
sampling data
• Incorporate new MRE and
metallurgical work to underpin
mining studies to demonstrate
potential project economics and
progress Mining Approvals
Drone over the Tallebung Tin Mining Field – Old Crusher and ROM to Southern Open Pit
PROGRESSING WORK PROGRAM LARGE-SCALE
EXPANSION DRILLING & MINING STUDIES
16
ASX: SKY
TALLEBUNG TIN PROJECT
LOW-RISK PATHWAY SET TO ADD VALUE QUICKLY
17
ASX: SKY
Schematic Plan View - Doradilla Tin Deposit
Exploration Target and extensions over geological map.
• Large-scale Tin Project in north-western NSW
• Recent metallurgical breakthrough shows ~78% of tin is
recoverable into a saleable concentrate
• Initial Exploration Target for 2.5km strike1,2:
• Potential to triple already large-scale shown by strike extensions:
• +2.5km to the NE from SKY drilling results
• +2.5km to the SW in historic drilling not digitised in SKY’s
database
• Potential development to compliment Tallebung, adding
substantial depth to SKY’s tin inventory pipeline
1For further details on the Exploration Target please see SKY ASX Announcement 14 July 2025 and Appendix 2.
2Please see the Cautionary Statement regarding Exploration Targets in the Disclaimer on Slide 2 and Appendix 2.
Exploration
Target
Tonnage Range Grade Range Contained Metal
Mt Tin (%) Tin (t)
Total @ 0.20%
tin cut-off grade
10 - 15 0.32 - 0.42 32,000 - 63,000
DORADILLA TIN PROJECT
A GIANT IN WAITING
18
ASX: SKY
BUILDING AUSTRALIA’S
FUTURE TIN PRODUCTION
SKYMETALS.COM.AU
ASX: SKY
Details on the MRE and Exploration Target for Tallebung can be found in SKY
ASX Announcement 23 January 2024, available at skymetals.com.au.
Exploration Target
The Exploration Target at Tallebung of approximately 23 – 32 Mt at a grade
ranging between 0.14 - 0.17 % tin has been defined from the drilling
completed prior to the estimate of the most recent MRE and Exploration
Target from 23 January 2024. The potential quantity and grade referred to as
the Exploration Target is conceptual in nature, as there has been insufficient
exploration to estimate a Mineral Resource and it is uncertain if further
exploration will result in the estimation of a Mineral Resource.
The drilling that was used to estimate the Exploration Target beyond the
current MRE has not been completed at sufficient drillhole or sampling
density to have these results included in the MRE at Tallebung
SKY has completed drilling of this Exploration Target in the months since the
estimate was completed. The new drilling results will be included in any
updated MRE or Exploration Target, with the aim to expand the MRE and
grow confidence in this estimated Exploration Target. At this stage it is not
certain what impact the latest drilling results will have in converting the
Exploration Target into Inferred or Indicated Resources or if it will increase
either the MRE or Exploration Target and work will be ongoing over the
coming months to assess these results.
Resource
Category
Tonnes Grade Contained Metal
Mt Tin (%) WO3 (%) Tin (kt) WO3 (mtu)
Inferred 10.6 0.14 0.03 15.2 302,106
Indicated 5.00 0.16 0.03 7.93 131,833
Total 15.6 0.15 0.03 23.2 433,940
Table 1 – Tallebung MRE showing total tonnage, grade and contained metals at a 0.08% Tin cut-off grade.
NB: WO3 refers to the Tungsten reported as an oxide as it is likely to be a significant by-product. Additionally,
mtu refers to metric tonne units which Tungsten is conventionally reported as, 1 mtu = 10 kg WO3.
Exploration
Target
Tonnes Grade
Mt Tin (%)
Upper 32 0.14 - 0.17
Lower 23 0.14 - 0.17
Table 2 – Tallebung Exploration Target with the upper
and lower tonnages and grade range presented.
APPENDIX 1: TALLEBUNG MRE
AND EXPLORATION TARGET ESTIMATE
20
ASX: SKY
Table 3 – Doradilla Tin Deposit: Initial Exploration Target for 2.5km of the total 7.5km strike
Exploration Target
Tonnage Range Grade Range Contained Metal
Mt Tin (%) Tin (t)
Total @ 0.20% tin
cut-off grade
10 - 15 0.32 - 0.42 32,000 - 63,000
APPENDIX 2:
DORADILLA EXPLORATION TARGET
Details on the Doradilla Exploration Target can be found in SKY ASX
Announcement 14 July 2025, available at skymetals.com.au.
Exploration Target
The Exploration Target at Doradilla of approximately 10-15 million tonnes (Mt)
grading 0.32-0.42% Sn, representing a potential 32,000 to 63,000 tonnes of
contained tin. The potential quantity and grade referred to as the Exploration
Target is conceptual in nature, as there has been insufficient exploration to
estimate a Mineral Resource and it is uncertain if further exploration will result in
the estimation of a Mineral Resource.
The drilling that was used to estimate the Exploration Target has not been
completed at sufficient drillhole or sampling density to have these results included
in an MRE.
To advance the Exploration Target toward Mineral Resource classification, the
following work is planned:
• Infill and step-out drilling to confirm continuity and geometry of mineralisation,
particularly to follow up:
- Multiple aircore holes returning intercepts >0.5% Sn over significant widths
with confirmed cassiterite-dominate mineralisation and,
- Newly recognised historic drilling which has not been digitised into SKY’s
drilling database.
• Metallurgical test work to assess tin recovery from oxide and sulphide zones to
continue to build on the excellent results achieved to date.
• Culminating in geological modelling and resource estimation in accordance
with JORC Code (2012).
21
ASX: SKY
Share your feedback
Discover