Tallebung Tin-Tungsten-Silver Project PFS Presentation
Released
Released
Announcement PDF
THREE CRITICAL METALS.
ONE SIGNIFICANT OPPORTUNITY.
TALLEBUNG PRE-FEASIBILITY STUDY CONFIRMS LOW COST,
HIGH-MARGIN AUSTRALIAN TIN-TUNGSTEN-SILVER PROJECT
INVESTOR PRESENTATION | 10 AUGUST 2026 | OLIVER DAVIES, MANAGING DIRECTOR AND CEO
ASX: SKY
Disclaimer
Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause actual results to be materially different from those expressed or implied by such forward looking information, including risks associated with investments in private
and publicly listed companies such as the Company; risks associated with general economic conditions; the risk that further funding may be required but unavailable for the ongoing development of the Company’s projects or future acquisitions; changes in government
regulations, policies or legislation; unforeseen expenses; fluctuations in commodity prices; fluctuation in exchange rates; litigation risk; restrictions on the repatriation of earnings by the Company’s subsidiaries; the inherent risks and dangers of mining exploration and operations
in general; risk of continued negative operating cashflow; the possibility that required permits may not be obtained; environmental risks; uncertainty in the estimation of mineral resources and mineral reserves; general risks associated with the feasibility and development of each
of the Company’s projects; foreign investment risks in Australia; changes in laws or regulations; future actions by government; breach of any of the contracts through which the Company holds property rights; defects in or challenges to the Company’s property interests;
uninsured hazards; disruptions to the Company’s supplies or service providers; reliance on key personnel and retention of key employees.
Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management of the Company made in light of their experience and their perception of trends, current conditions and expected developments, as well as other factors that
management believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. The Company believes that the assumptions and expectations reflected in such forward-looking information are
reasonable.
Assumptions have been made regarding, among other things: the Company’s ability to carry on its future exploration, development and production activities, the timely receipt of required approvals, the price of tin, gold, copper and base metals, the ability of the Company to
operate in a safe, efficient and effective manner and the ability of the Company to obtain financing as and when required and on reasonable terms. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Although
the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no
assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not
undertake to update any forward-looking information, except in accordance with applicable securities laws.
No Liability/Summary Information
The Company has prepared the Presentation Materials based on information available to it at the time of preparation. No representation or warranty, express or implied, is made as to the fairness, accuracy or completeness of the information, opinions and conclusions contained
in the Presentation Materials. To the maximum extent permitted by law, the Company, its related bodies corporate (as that term is defined in the Corporations Act 2001 (Commonwealth of Australia)) and the officers, directors, employees, advisers and agents of those entities do
not accept any responsibility or liability including, without limitation, any liability arising from fault or negligence on the part of any person, for any loss arising from the use of the Presentation Materials or its contents or otherwise arising in connection with it. Post 1989,
exploration results detailed in this presentation have previously been reported to the ASX or in the independent geologist report contained in the Prospectus lodged on 18 April 2019. Endowment = current resource plus production. Coordinate system on maps is MGA94 Zone55
unless otherwise stated.
Competent Persons Statement
The information in this report that relates to Exploration Results and the Doradilla Exploration Target is based on information compiled by Mr. Oliver Davies, who is a Member of the Australasian Institute of Geoscientists. Mr. Oliver Davies is an employee of Sky Metals Ltd and has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves.’ Mr. Davies consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
The information in this report that relates to the MRE Data is based on information compiled by Mr. Chris De-Vitry, who is a Member of the Australasian Institute of Geoscientists and the AUSIMM. Mr. Chris De-Vitry is independent of Sky Metals Ltd and has sufficient experience
which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves.’ Chris De-Vitry consents to the inclusion in this report of the matters based on his information, in the form and context in which they appear.
Cautionary Statement regarding Exploration Targets
An Exploration Target of 10 – 15 Mt @ 0.32-0.42% Tin for the Doradilla Project (please see SKY ASX Announcement SKY ASX Announcement 14 July 2025 for details). The potential quantity and grade referred to in this presentation as Exploration Targets are conceptual in nature,
as there has been insufficient exploration to estimate a Mineral Resource and it is uncertain if further exploration will result in the estimation of a Mineral Resource. SKY will continue drilling of these exploration targets in the coming months with the aim to grow confidence in
estimated Exploration Targets. Supporting report and further details on the Exploration Target are included in SKY ASX Announcement 14 July 2025.
2
ASX: SKY
DISCLAIMER – IMPORTANT INFORMATION
ASX: SKY
3
TALLEBUNG PROJECT PRE-FEASIBILITY STUDY
CONFIRMS A SIMPLE, ROBUST AND LOW-RISK PROJECT
ASX: SKY
Base case
US$5,653/t
AISC per tin tonne
produced (net co-products)
Spot case
-US$18,935/t
AISC per tin tonne
produced (net co-products)
Highlights
• 3Mtpa open cut project with a 1.99:1 strip ratio
• Initial mine life of 7.3 years from only 66% of the total MRE
• Average annual production of:
• 2,040t of tin
• 31,700mtu of tungsten trioxide
• 315koz of silver
• Low capex of A$138.8M, short lead times and 7-month construction
schedule
• Extensive testwork confirms exceptional ore sorting performance
enabling a 500ktpa downstream processing plant
• Resource remains open in all directions with drilling recommenced
targeting mine life extension for the DFS
• Approvals underway with first production targeted for mid-CY2028
Metric Base Case1 Spot Case2
NPV8 (pre-tax) A$438M A$1.0B
Annual EBITDA
(avg.)
A$116M A$221M
IRR (pre-tax) 69% 130%
Capital
payback
18 months 9 months
ASIC – All-In Sustaining Cost
1Base case pricing assumptions: US$45,000/t Sn, US$1,500/mtu WO3 and US$50/oz Ag.
2Spot case pricing assumptions: US$56,450/t Sn, US$3,075/mtu WO3 and US$61.90/oz Ag.
4
TALLEBUNG PROJECT PRE-FEASIBILITY STUDY
SIMPLE MINING AND PROCESSING
ASX: SKY
• Simple single open-pit mining operation with a low
1.99:1 life-of-mine strip ratio
• +4 years of metallurgical testwork confirm simple,
low-risk processing of coarse tin, tungsten and silver
mineralisation
• Exceptional ore sorting pre-concentration performance
demonstrated across multiple test programs
• 75t bulk sample sorting testing achieved >90% mass
reduction while maintaining high tin, tungsten and
silver recoveries
• Pre-concentration reduces downstream processing
capacity from 3.0Mtpa to ~0.5Mtpa, significantly
lowering capital and operating costs
• Conventional gravity processing then produces separate
tin and tungsten concentrates, plus silver doré
Tin 79%
Tungsten 60%
Silver 50%
Conceptual overview of Tallebung mine and infrastructure layout
Revenue split by commodity (base case)
Metal Recoveries over Life of Mine
TIN 61%
TUNGSTEN 29%
SILVER 10%
GROWING LARGE HARDROCK RESOURCE
Top: 3D oblique view of updated MRE block model coloured by total NSR with an optimised pit shell.
Bottom: Cross-sections showing the block model coloured by total NSR with pit shell looking NNW.
• Only ~60% of latest MRE included in the PFS Mine Life
• Latest MRE still remains open in all directions
• Updated MRE exceeded the previous Exploration Target:
• 32.7Mt @ 0.16% Tin Equivalent1 for 36.8kt of
contained tin, 1.14M mtu of WO₃ and 9.94Moz
of contained Ag
• Over 4,000m of drilling completed since the MRE update
• Drilling already underway targeting Resource growth and
upgrade of MRE confidence to support longer mine life
• MRE update demonstrated exceptional conversion of
Inferred Resources to Measured and Indicated Resources
required to support extended mine life
1For further details on the MRE update and tin equivalent (SnEq)
please see SKY ASX Announcement 13 July 2016 and Appendix 1.
5
ASX: SKY
• New intercepts show potential for additional shallow, higher-grade tin,
tungsten and silver not included in the updated MRE
• Multiple shallow target areas identified for continued Resource growth:
• Strong tungsten potential confirmed in latest drilling TBRC218:
6m @ 1.32% W, 20.2g/t Ag & 0.10% Sn from 21m
• Results demonstrate that the deposit remains open in all directions
• New results not included in MRE upgrade and PFS also include:
TBRC427: 9m @ 0.54% tin, 0.11% tungsten & 205g/t silver from 67m
TBRC436: 14m @ 0.58% tin & 0.04% tungsten from 1m
GROWING HIGH-GRADE TIN-TUNGSTEN-SILVER
DISCOVERIES AND EXTENSIONS
6
ASX: SKY
Cross-section
of new drilling
since MRE
update
showing newly
discovered
mineralisation
7
TALLEBUNG PROJECT
LOW CAPITAL COST TO STRONG CASHFLOWS
ASX: SKY
Processing Plant layout
• Low pre-production capital of A$138.8M (excluding
contingency) comprising A$113.4M processing plant
and A$26.3M site and mine establishment costs
• Conventional off-the-shelf processing equipment
supports a simple flowsheet, short lead times and a
rapid 7-month construction schedule
• Strong infrastructure advantage with grid power at
site and local water sources significantly reducing
development risk
• Well-positioned regional location with Condobolin
just ~70km away, providing access to a skilled mining
workforce and services
• Clear pathway to development, targeting mining
approvals in late CY2027 and first production by mid-
CY2028
• Low operating costs of ~A$98 million per annum for
a 3Mtpa operation, supported by a low strip ratio of
1.99:1 and a simple gravity-based processing
flowsheet:
• Mining costs of ~A$49 million per annum,
equivalent to a life-of-mine average of A$5.45/t
mined (ore and waste) using contract mining
• Processing costs of A$35 million per annum, or
A$11.90/t ROM processed, including A$3.75/t
crushing costs before ore sorting and processing
• Site operating costs of A$13 million per annum,
including power, water supply, freight and site
administration
• Coarse, near-surface tin-tungsten-silver
mineralisation and the absence of large-scale
chemical processing support low operating costs,
simplified approvals and straightforward project
construction and operation
8
TALLEBUNG PROJECT
SIMPLE, LOW-COST OPERATION
ASX: SKY
Simplified flowsheet schematic
Tallebung Project - Simplified PFS Flowsheet
Mining /
ROM Feed
3.0 Mtpa
Crushing
Rejects /
Tailings
~2.5 Mtpa
Preconcentration
reject / waste
~500 ktpa
Ore Sorting + Coarse
Gravity Preconcentration
Crushing
Gravity &
Dressing
Circuit
Ore sorting +
Coarse Gravity
3.0 Mtpa -> -0.5 Mtpa
Tin
Concentrate
10t/day
(~3,000t/year)
Tungsten
Concentrate
1.25t/day
(~450t/year)
Silver Dore
~1 kOz/day
(~350t/year)
9
TALLEBUNG PROJECT
STRONG CASHFLOWS
ASX: SKY
Metric Base Case¹ Spot Case²
Annual revenue A$222M A$332M
Annual operating costs A$98M A$98M
AISC per tonne of tin
(net of co-products)
US$5,653/t –US$18,935/t
Average annual EBITDA A$116M A$221M
Annual free cashflow
(post-tax)
A$64M A$138M
Pre-tax NPV₈ A$438M A$1.0B
IRR 69% 130%
Capital payback 18 months 9 months
1 Base case pricing: US$45,000/t Sn, US$1,500/mtu WO3 and US$50/oz Ag.
2 Spot case pricing: US$56,450/t Sn, US$3,075/mtu WO3 and US$61.90/oz Ag.
• Brownfields, highly disturbed historical mine site
• NSW State Significant Development (SSD) Scoping Report
approved, marking a major milestone in the project approvals
pathway
• Environmental Impact Statement (EIS) studies underway,
supporting targeted NSW Government approval in 2027
• Environmental permitting substantially de-risked, with key
baseline studies already completed or well advanced:
• More than two years of groundwater monitoring completed
• Geochemical characterisation completed
• Over 12 months of on-site meteorological data collected
• Biodiversity studies well advanced to support EIS
10
TALLEBUNG PROJECT
RAPIDLY ADVANCING APPROVALS
ASX: SKY
Tallebung Tin Mine – Aerial Image of Historical Mining and Infrastructure.
TALLEBUNG TIN PROJECT
FUTURE WORK PLANS
11
ASX: SKY
Year 2026 2027 2028
Quarter Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Month/End of Quarter June September December March June September December March June
Project
Development
Updated MRE Completed
Baseline Environmental Studies Completed
Release Pre-Feasibility Study Completed
Definitive Feasibility Studies Commencing
Mining
Approvals
Submit NSW State Significant
Development (SSD) Scoping Report
Completed
Receive SEARs from NSW
Government
Completed
Prepare Environmental Impact
Statement
Commencing
Mining Lease (ML) Application
Community & Stakeholder
Consultation
Project
Construction
Project Infrastructure Licences –
Water, Power, etc.
Final Investment Decision (FID)
Plant Commissioning and
Production Ramp-up
• Definitive Feasibility Study
commencing to support a
Final Investment Decision
• Environmental Impact
Statement in preparation,
targeting NSW mining
approval in 2027
• Drilling resumed to grow the
MRE and extend mine life
beyond initial 7.3 years
• Existing A$17.6M cash
balance to fund near-term
work program
• Active engagement
underway with strategic
funding and offtake partners
to underpin development
TIN + SILVER + TUNGSTEN – ALL AT TALLEBUNG
ASX: SKY 12
Source: https://www.goldbullionaustralia.com.au/live-charts-prices/
SILVER PRICE
Source: LME
TIN PRICE
Tungsten is traded in metric tonne units (mtu), 1 mtu = 10 kg WO3, $3,000/mtu = $300,000/t
Source: Fastmarkets, / SMM – APT 88.5% WO3, CIF Rotterdam, US$/MTU
TUNGSTEN PRICE
• Fundamental structural demand growth – triggering a supply crunch after 30+ years of under-investment
• Tin is vital for EVs, Renewable Energy, AI and all electronics
• New solar PV tech increases tin use
• Tin replacing lead and indium in new PSC solar cells
Source: BNEF, Rho
Motion, Macquarie
Strategy – March 2026
Increase
in
tin
demand
Tin
Price
ASX: SKY
TIN PRICE – INCREASING WITH GLOBAL DEMAND
13
TIN: ESSENTIAL ELECTRIFICATION METAL
– GLOBAL SUPPLY DISRUPTIONS
14
ASX: SKY
• Inelastic tin price – strong demand
underpinned by tin’s irreplaceable role in
electronics, increasing demand with AI and EVs
• Over 6% of world tin production cut when
Alphamin’s Bisie tin mine shut in DRC – M23
rebels still active along with other risks to
threaten production as seen in 2025 when
production was halted
• Heavily disrupted Indonesian tin production
decreased by 33% in 2024 – previously
Indonesia accounted for 20% of global tin
supply
• Limited reliable and ethical sources
• Few tin investment opportunities on ASX
Source: ITA (March 2026)
BUILDING AUSTRALIA’S
FUTURE TIN, TUNGSTEN AND
SILVER PRODUCTION
SKYMETALS.COM.AU
ASX: SKY
16
SKY INVESTMENT SNAPSHOT
CREATING A NEW AUSTRALIAN TIN PRODUCER
ASX: SKY
TALLEBUNG
SYDNEY
DORADILLA
CORNERSTONE ASSET
Flagship Tallebung Tin-Tungsten-Silver Project in NSW
– Initial mine life PFS: 69% IRR and +AU$100m annual
EBITDA supporting advancing rapidly development
QUALITY TEAM
Highly regarded board & leadership
team with exceptional track record,
led by Norm Seckold and Oliver Davies
TIN & TUNGSTEN MARKETS
Compelling market outlook for tin and tungsten,
driven by their irreplaceable use in modern
technologies while both facing supply constraints
ASSET PIPELINE
Building a strong pipeline of emerging
development assets that now includes
the Doradilla Tin Project
VALUE
Compelling value proposition with a
market capitalisation strongly
leveraged to growth
NEAR-TERM CATALYSTS
Pre-Feasibility Study highlights Tallebung's
potential as a low-Capex, low-Opex
development opportunity
EXPERIENCED AND PROVEN MANAGEMENT
NORMAN SECKOLD | CHAIRMAN
30+ years in the full-time management of natural
resource companies. Past Chairman and Director of
listed companies including Bolnisi Gold NL, Timberline
Minerals Inc., Perseverance Corporation Ltd, Valdora
Minerals NL, Palmarejo Silver and Gold Corp, Kings
Minerals NL, Mogul Mining NL, and Santana Minerals
Ltd. Currently Chairman Nickel Industries Ltd, Alpha HPA
Ltd, Fulcrum Lithium Ltd and Minerals Exploration Ltd.
OLIVER DAVIES | MANAGING DIRECTOR
At SKY since listing in 2019. Previously in exploration and
operational roles with Evolution Mining and Alkane
Resources in NSW and Qld. Mr. Davies has worked closely
on several successful NSW discoveries including Evolution
Mining’s significant expansion at the Lake Cowal Gold
Mine and Alkane’s exploration success with the
discoveries at Tomingley and Boda.
RIMAS KAIRAITIS | NON-EXECUTIVE DIRECTOR
25+ years experience in minerals exploration and resource
development in gold, base metals and industrial minerals.
Mr. Kairaitis was founding Managing Director and CEO of
Aurelia Metals, which he steered from a junior exploration
company to a profitable NSW based gold and base metals
producer. Mr. Kairaitis is also the founding Managing
Director and current Executive Director of Alpha HPA Ltd.
RICHARD HILL | NON-EXECUTIVE DIRECTOR
25+ years experience in the mineral resources sector as a
geologist and solicitor. Mr. Hill has a successful track record
of guiding ASX listed mining companies from the exploration
and discovery phase through to development in a range of
commodities. These have included past roles as founding
Director for Aurelia Metals Ltd and as former Chairman of
New World Resources Ltd and Genesis Minerals Ltd as well
as current Chairman of Accelerate Resources Ltd.
Shares on issue
Options & Performance Rights
Share price (3 Aug 2026)
Market capitalisation
Cash (30 June 2026)
Debt
CAPITAL STRUCTURE
992.3M
12.15M
~$0.24
~$221M
~$17.6M
Nil
SHAREHOLDERS
Top 20 holders
Board and Management
53.3%
12.6%
EXPERT GUIDANCE | SKY’s CONSULTANTS
Tallebung Environmental Mining Approvals: AARC and R.W. Corkery & Co.
to expedite and advise on best practice for environmental studies and
mining approvals process.
Tallebung Metallurgy: Mineral Technologies, Gunn Metallurgy, TOMRA
Ore Sorting Solutions, ALS Burnie and ALS Perth advancing studies
17
ASX: SKY
SCOTT TODD | EXECUTIVE DIRECTOR
+30 years experience across operations, commercial
management, and project development. Previous roles
include COO at PYBAR, VP at Mitsubishi Development, and
NSW Mining Division Manager at Thiess. Most recently, Mt
Todd was General Manager – Delivery at North Harbour
Clean Energy, navigating major developments through the
NSW planning and approvals process.
• Tin discovered in the 1890s and mined into the mid-1980s
• Small shafts and open pits mined hard rock tin veins,
culminating in large scale alluvial mining production in the
1960s-70s
• Infrastructure already in place from previous mining
includes:
• Powerlines to site
• Excellent road access
• Hard-rock tin source remains intact and largely unmined
• Large-scale tin deposit now defined over 2km and still
growing with every hole
18
MAJOR HISTORICAL OPERATION
TALLEBUNG PROJECT
ASX: SKY
Tallebung Tin Mine – Aerial Image of Historical Mining and Infrastructure.
TALLEBUNG PROJECT
KEY COMPETITIVE ADVANTAGES
19
ASX: SKY
• Low-Cost Mining Proposition – Shallow
deposit at surface, very low strip ratio and
growing with every new drill-hole
• Exceptional Upgrade – Ore sorting ideally
suited to the deposit – increases grade >10x,
removing over 90% of mined mass in high tin
recovery bulk testwork
• Low-Cost Processing – Simple gravity circuit
for a saleable tin concentrate
• High Payability on Tin Concentrate – over
90% payability on a +60% tin concentrate,
with sample tin concentrate from bulk sample
metallurgical program available shortly
Tallebung Tin Mine – Drone Photo looking East down the Central Lead Open Pit.
• Tallebung tin deposit is ideally matched to ore sorting
technology
• Conservative, Stage 1 bulk TOMRA Ore Sorting
testwork demonstrated increases in grade of +1000%
and rejects +90% of mass
• Resource grade increases from 0.15% tin x 10 =
over 1.50% tin with 95% tin recovery
• Reduced mass means smaller, lower plant costs to
produce a saleable tin concentrate
• Bulk sample of +75t of mineralisation was excavated,
crushed and ore sorted on a full-scale TOMRA ore
sorter to optimise process, culmination of more than
3 years of testwork
Accepted
Rejected
Schematic of a TOMRA
XRT Ore Sorter
Cassiterite from Tallebung –
Scale in mm
Dense tin – cassiterite “nuggets”
detected by ore sorter and accepted
Host rock and quartz vein without
tin rejected by ore sorter
The image of cassiterite from Tallebung is intended for illustrative
purposes only and SKY does not intend to assay this sample.
TOMRA-HIGH TECHNOLOGY CHANGES THE GAME
20
ASX: SKY
• Extremely effective sorting of Tallebung
tin achieved, as tin is ideally present as
large, discrete ‘chunks’, easily classified
by the TOMRA XRT ore sorter
• 75t bulk sample testwork on full-scale
ore sorters demonstrate:
– Stage 1 Sorting: Tin upgraded from
0.17% Sn to 2.32% Sn (a 13x increase)
with +94.8% Sn recovery in total.
– Stage 2 Sorting: Further upgrade to
10.8% Sn (a further 4.6x increase on
Stage 1) with a +70% Sn recovery.
• Over 90% mass reduction significantly
reduces any future project CAPEX and
OPEX
TOMRA-HIGH TECHNOLOGY CHANGES THE GAME
21
ASX: SKY
• Groundwater Monitoring Bores – over 2 years of
required monitoring now completed
• Geochemical Characterisation – Initial deposit
characterisation completed, weathering only
variable
• Weather Station – Installed over 1 year ago with
required data collected
• Biodiversity Study – Initial background study
completed with seasonal and detailed studies
progressing
• Environmental Program entering formal EIS stage
now in preparation for mining approval
• Pilot-scale plant testwork providing crucial data to:
• Optimising the metallurgical flowsheet
• Produce tin concentrate for end-user
marketing
• Increase confidence in Resource Estimation
PROGRESSING WORK PROGRAM:
PAVING WAY TO MINING
22
ASX: SKY
Goat-proof
fence
Weather station
and mast
Tallebung Weather Station
Trench T5 while being excavated – looking
north towards the edge of the Southern
Open Pit with the walls in background
• Large-scale tin project in north-western NSW
• Recent metallurgical breakthrough shows ~78% of tin
is recoverable into a saleable concentrate
• Initial Exploration Target for 2.5km strike1,2:
• Potential to quadruple already large-scale shown by
strike extensions:
• +5km to the SW in historical drilling and new SKY
rock chip sampling
• +2.5km to the NE from SKY drilling results
• Potential development to complement Tallebung,
adding substantial depth to SKY’s tin inventory pipeline
• Expansion drilling program planned for the coming months
1For further details on the Exploration Target please see SKY ASX Announcement 14 July 2025 and Appendix 2.
2Please see the Cautionary Statement regarding Exploration Targets in the Disclaimer on Slide 2 and Appendix 2.
Exploration
Target
Tonnage Range Grade Range Contained Metal
Mt Tin (%) Tin (t)
Total @ 0.20%
tin cut-off grade
10 - 15 0.32 - 0.42 32,000 - 63,000
DORADILLA TIN PROJECT
A GIANT UNLOCKED
23
ASX: SKY
Schematic Plan View - Doradilla Tin Deposit
Exploration Target and extensions over magnetics map.
Details on the MRE for Tallebung can be found in SKY ASX Announcement 13 July 2026,
available at skymetals.com.au.
Multi-commodity metal resources within the Tallebung Deposit were defined using a cutoff
calculated for a Net Smelter Return (NSR) equation. This equation combines conservative
base-case commodity prices, recovery factors for each of Sn, W, and Ag, and concentrate
payability factors to classify resources.
Tin resources recently estimated in NSW for open pit mining have previously used a 0.05%
tin cut-off grade. At a standalone tin grade of 0.08% Sn, the previous cutoff grade used at
Tallebung (SKY ASX Announcement 23 January 2024), an NSR of approximately 23.34 USD/t
is given by the equation in Table, hence, to account for the multicommodity nature of the
mineralisation the MRE has used a cutoff of US$20/t as calculated in Table 2 below.
Table 1 – Tallebung MRE showing total tonnage, grade and contained metals at a US$20/t NSR cut-off grade. NB: Previous MRE cut-off of 0.08% Sn without any WO3 or Ag
credits equates to a ~US$23/t NSR at the base case Tin price of US$37500/t. Additionally, WO3 refers to the Tungsten reported as an oxide for which it is sold and “mtu” refers
to metric tonne units as Tungsten is conventionally reported in, 1 mtu = 10 kg WO3.
APPENDIX 1: TALLEBUNG MRE
24
ASX: SKY
MRE Classification
Tonnes Grade Contained Metal
Mt Sn Eq (%) Sn (%) WO3 (%) Ag (g/t) Sn (kt) WO3 (MTU) Ag (koz)
Measured 0.5 0.22 0.19 0.033 8.3 0.9 16,171 130
Indicated 12.3 0.17 0.14 0.029 8.5 17.0 356,035 3,349
Inferred 19.9 0.15 0.09 0.039 10.1 18.8 767,628 6,461
Total 32.7 0.16 0.11 0.035 9.5 36.8 1,139,835 9,940
Metal Price/Unit Recovery Concentrate Payability
Sn US$37,500/t
Sn Grade (%) >0.05%
94.04+(6.43xLoge (Sn
Grade (%)))
95%
Sn Grade (%) <0.05% Sn Grade (%) - 0.015%
Sn Grade (%) <0.015% 0
W US$1,000/MTU 60% 70%
Ag US$50/oz 40% 90%
NSR (USD/t)= (("Sn Grade (%)"*(IF("Sn Grade (%)">0.05,94.04+(6.43*LN("SnGrade (%)")),IF(("Sn Grade"-0.01)>0,((“SnGrade
(%)” -0.015)/"SnGrade (%)")*100,0))/100))*0.95*37500/100)+((("WGrade (ppm)"/10000)*0.6)*0.7*1000)+((("AgGrade
(g/t)"/31.1034768)*0.9*0.4)*50)
Sn Equivalent (SnEq) = (((((“SnGrade (%)”)*(IF((“SnGrade (%)”)>0.05,94.04+(6.43*LN(“SnGrade (%)”)),IF(((“SnGrade (%)”)-
0.01)>0,(((“SnGrade (%)”)-0.015)/(“Sn Grade (%)”))*100,0))/100))/100)*37500)+((("W Grade
(ppm”)*(231.9/183.9))*0.6)/1000000)*(1000*100)+(("Ag Grade (g/t)"/ 31.1034768)*0.4)*50)/37500*100
Table 2 – Net Smelter Return (NSR) Price and Recovery Factors
with equations for calculating Tin Equivalent (Sn Eq) and NSR.
Table 3 – Doradilla Tin Deposit: Initial Exploration Target for 2.5km of the total 7.5km strike
Exploration
Target
Tonnage Range Grade Range Contained Metal
Mt Tin (%) Tin (t)
Total @ 0.20% tin
cut-off grade
10 - 15 0.32 - 0.42 32,000 - 63,000
APPENDIX 2:DORADILLA EXPLORATION TARGET
Details on the Doradilla Exploration Target can be found in SKY ASX Announcement 14 July 2025, available at skymetals.com.au.
Exploration Target
The Exploration Target at Doradilla of approximately 10-15 million tonnes (Mt) grading 0.32-0.42% Sn, representing a potential 32,000 to 63,000 tonnes of contained
tin. The potential quantity and grade referred to as the Exploration Target is conceptual in nature, as there has been insufficient exploration to estimate a Mineral
Resource and it is uncertain if further exploration will result in the estimation of a Mineral Resource.
The drilling that was used to estimate the Exploration Target has not been completed at sufficient drillhole or sampling density to have these results included in an MRE.
To advance the Exploration Target toward Mineral Resource classification, the following work is planned:
• Infill and step-out drilling to confirm continuity and geometry of mineralisation, particularly to follow up:
• Multiple aircore holes returning intercepts >0.5% Sn over significant widths with confirmed cassiterite-dominate mineralisation and,
• Newly recognised historic drilling which has not been digitised into SKY’s drilling database.
• Metallurgical test work to assess tin recovery from oxide and sulphide zones to continue to build on the excellent results achieved to date.
• Culminating in geological modelling and resource estimation in accordance with JORC Code (2012).
25
ASX: SKY