Quarterly Activities Report - March 2025
Released
Released
Announcement PDF
TALLEBUNG TIN PROJECT, NSW
• Significant high-grade extensions to the Tallebung deposit confirmed, with strong tin
mineralisation intersected in all five diamond drill-holes completed during the quarter.
Results include:
▪ TBD018: 6.65m @ 1.01% tin from 52.35m, including:
2.65m @ 2.46% tin & 0.17% tungsten from 52.35m.
▪ TBD015: 17.9m @ 0.25% tin from 9.1m, including:
1.1m @ 2.92% tin, 51.6g/t silver & 0.44% tungsten from 9.1m.
▪ TBD014: 19.25m @ 0.20% tin from 10.1m, including:
3.55m @ 0.79% tin from 25.8m.
• Four bulk samples for a total of over 60 tonnes of tin mineralisation successfully excavated
and crushed in preparation for a pilot-scale metallurgical program, aimed at:
▪ Optimising the entire metallurgical flowsheet;
▪ Producing tin concentrate for ongoing marketing and end-user engagement;
▪ Evaluating tungsten and silver by-product recoveries; and
▪ Increasing confidence in resource estimation with tin produced from the bulk
samples to be reconciled with the grade estimate to validate the MRE model.
• Major multi-rig Reverse Circulation (RC) drilling program commenced in early April to help
progress Tallebung towards commercial development by:
▪ Building on deposit extensions delineated by diamond drilling; and
▪ Targeting substantial growth in the existing Mineral Resource Estimate (MRE)1
in terms of size, grade and confidence ahead of mine development studies,
targeted for completion by mid-CY2025.
CORPORATE
• SKY stands well-funded with over $5M in cash as at 31 March 2025.
1
For further details on the MRE for the Tallebung Tin Project please see SKY ASX Announcement 23 January 2024.
+61 2 6360 1587
2 HAWTHORN PLACE, ORANGE NSW 2800
WWW.SKYMETALS.COM.AU
ABN 46 098 952 035
JUNE 2025 QUARTER – PROPOSED WORK PROGRAM
TALLEBUNG PROJECT
• Major Reverse Circulation (RC) drilling program targeting ongoing Resource expansion.
• Metallurgical testwork on bulk samples to optimise the process flowsheet and produce
marketable tin concentrates to aid in offtake marketing.
• Pilot-scale gravity plant testwork to produce saleable tin concentrate.
• Pending release of a mining study to consolidate the economic potential at Tallebung.
The Board of Sky Metals Limited (‘SKY’ or ‘The Company’) is pleased to provide a Quarterly Activities Report
outlining SKY’s exploration and development programs during the March 2025 Quarter.
TALLEBUNG PROJECT (EL 6699, SKY 100%)
DIAMOND DRILLING PROGRAM
Sky Metals undertook a diamond drilling program at the Tallebung Project during the March Quarter, with five
diamond holes completed to provide high-quality data to further improve the Company’s geological understanding
of the deposit, vital to upgrading the MRE and to provide the basis for ongoing mining and development studies.
Assay results were reported subsequent to quarter-end, confirming significant extensions to the Tallebung
deposit. Tin mineralisation was intersected in all five diamond drill-holes.
The first hole in the program, TBD014, confirmed extensions to the existing MRE. The hole was drilled outside of
the eastern margin of the existing MRE and targeted down-dip extensions to newly discovered historic workings
at surface, which had not been previously drill tested (Figure 1).
Significant visual tin mineralisation encountered in this first drill-hole showed that the tin mineralisation is
continuous at depth and extends to the east of the existing (Figure 2) MRE. Assay results have confirmed the
significant visual mineralisation, with results including:
TBD014:
19.25m @ 0.20% Sn from 10.1m, including:
3.55m @ 0.79% Sn, 13.9g/t Ag & 0.02% W from 25.8m.
The second and third holes (TBD015 & TBD016) in the program targeted outcropping tin veins in the southern open
pit as well as extensions to TBRC0902, where the Tallebung deposit was extended to the east with results including:
TBRC090: 10m @ 0.69% Sn, 23.7g/t Ag & 0.03% W from 23m, including:
2m @ 2.68% Sn, 51.4g/t Ag & 0.06% W from 28m.
Both of these holes successfully intersected further tin mineralisation and expanded the deposit to the east of the
current extents of the existing MRE, with results including:
2
TBD015:
17.9m @ 0.25% Sn, 6.95g/t Ag & 0.06% W from 9.1m, including:
1.1m @ 2.92% Sn, 51.6g/t Ag & 0.44% W from 85m.
5m @ 0.14% Sn from 172.3m, including:
0.6m @ 0.91m & 0.04% W from 172.3m
TBD016:
29.9m @ 0.12% Sn, 5.03g/t Ag & 0.02% W from 45.2m, including:
3.5m @ 0.38% Sn, 18.3g/t Ag, 0.02% W from 53.5m.
14m @ 0.16% Sn from 89.8m, including:
3.2m @ 0.60% Sn & 0.44% W from 89.8m.
Please see SKY ASX Announcement 17 July 2024 for further information.
2
Figure 1: Plan showing the location of the diamond drill-holes in latest program as well as existing highlight drill
intercepts and the boundary of the existing Tallebung MRE shown over geology.
The fourth and fifth holes (TBD017 & TBD018) in the program both intersected exceptional visual tin mineralisation
within the newly discovered southern extension of the deposit. Assay results included:
TBD017:
0.65m @ 1.22% Sn & 0.06% W from 37.35m, including:
14.8m @ 0.14% Sn & 38.5g/t Ag from 57.2m, including: 0.75m @ 1.14% Sn & 187g/t Ag
from 57.2m.
TBD018:
6.65m @ 1.01% Sn from 52.35m, including:
2.65m @ 2.46% Sn & 0.17% W from 52.35m.
TBD018 intersected a shallow, wide quartz veined interval hosting abundant cassiterite (tin-oxide) throughout with
grains of wolframite (tungsten) observed, typically associated with the tin mineralisation at Tallebung (see SKY
ASX Announcement 1 April 2025).
3
Figure 2: Cross-section of TBD014 with previous drilling and highlighting the extension to the eastern margin of
known tin mineralisation at Tallebung. Section looking north-west and depth shown as metres below surface.
These holes have successfully identified additional tin-tungsten mineralisation at Tallebung and will also
contribute to increasing the Company’s geological understanding of the deposit, improving its geological models
and increasing confidence in future upgrades of both the MRE and the Exploration Target.
EXTENSIVE RESOURCE GROWTH-FOCUSED RC DRILLING PROGRAM
Approvals were received during the Quarter and a drill contractor appointed for a Reverse Circulation (RC) drilling
program comprising approximately 70 RC holes for more than 8,000m of drilling. The program commenced in early
April aimed at extending new zones of higher-grade tin mineralisation discovered beyond the margins of the known
tin resources at Tallebung.
A significant number of shallow RC holes are also planned in southern area of the existing MRE to expand the
higher confidence Indicated Resources within the MRE in areas where future mining is likely to be focused in the
early stages of operations to extract higher-grade, shallow tin mineralisation to facilitate a rapid capital payback.
Once all the results from this program are received, an updated MRE will be completed to enable Scoping and
Feasibility Studies to be released.
4
The RC drilling program will also target extensions to the higher-grade tin mineralisation discovered in previous
drilling programs completed in 2024. This drilling is designed to exploit opportunities to delineate additional
shallow, higher grade mineralisation that will also underpin the goal of achieving a faster payback of project
CAPEX by incorporating these areas in the early stages of the mine plan.
Two RC drill rigs will be utilised to expedite the program and provide results quickly to build on the existing MRE
at Tallebung. Drilling is expected to be completed by May with results expected to flow from May onwards.
TRENCHING AND BULK SAMPLING PROGRAM
Following the completion of a trenching program for bulk metallurgical testwork and MRE validation at Tallebung
during the December 2024 Quarter, assay results were reported during the March 2025 Quarter, with all trenches
successfully intersecting tin mineralisation at surface, providing valuable insights into the geology at Tallebung
(see Figure 3).
Figure 3: Plan showing the location of the samples excavated for the bulk sampling program in orange as well as
existing drilling, highlight drill intercepts and the boundary of the existing Tallebung MRE shown over geology.
Results from the trenching and bulk sampling program included:
T4:
3m @ 0.16% Sn from 12m along trench.
5
T5:
10m @ 0.15% Sn & 0.02% W from 22m along trench (NB: includes 2.8m from 28-30.8m where no
sample was taken due to an interceding channel removing bedrock between 28-30.8m, therefore
intercept is calculated with 0.00% Sn used for 28-30.8m accordingly), including:
6m @ 0.20 % Sn & 0.02% W from 22m along trench, including:
1m @ 0.44% Sn & 0.03% W from 22m along trench.
T6:
1m @ 0.19 % Sn & 8.41g/t Ag from 41m along trench.
T7:
4.9m @ 0.37% Sn from 8m along trench (NB: intercept was terminated on zone of historic selective
mining which had been deeply excavated immediately adjacent to the intercept), including:
0.9m @ 1.15% Sn from 12m along trench (immediately adjacent to selectively mined zone).
T8:
1m @ 0.15% Sn & 12.1g/t Ag from 2m along trench; and
2m @ 0.18% Sn & 0.03% W from 30m along trench.
T9:
6m @ 0.08% Sn, 0.03% W & 48.3g/t Ag from 11m along trench, including:
1m @ 0.24% Sn, 0.10% W & 221g/t Ag from 11m along trench.
In the case of the best two results in T5 and T7, both trenches had zones where the trench did not have bedrock
to be sampled. In T5, an erosional channel had removed a zone within the mineralised tin intercept, and in T7
historic selective mining had extracted a section of the bedrock immediately adjacent to where the best trenching
assay result was returned.
As a result of these factors, the results from of these trenches might have been significantly higher in grade and
width had these areas been intact and present to be sampled. Regardless, the trenching results will be
incorporated into the geological model to increase both the size and confidence in the MRE.
Four (4) bulk samples for a total of over 60 tonnes of tin mineralisation were successfully excavated and crushed
during the March 2025 Quarter in preparation for a pilot-scale metallurgical program.
The bulk sampling sites were selected to target variation of deposit tin grades and traverse zones across the entire
footprint of the currently defined extent of the Tallebung tin mineralisation.
The four bulk samples were crushed to -40mm and screened to remove the -7mm fines from the sample.
The 7-40mm sample and the -7mm fines have been transported to TOMRA Ore Sorting Solutions in Sydney. The 740mm sample will be ore sorted on a full-scale, commercial TOMRA XRT Ore Sorter to produce a high-recovery
product.
The high-recovery ore sort product will then be sorted a second time to produce a high-upgrade ore sorting
product where up to over 95% of the mass may be rejected. The reject from the second ore sort will be combined
with the -7mm fines sample.
The second ore sort product will be transported directly to ALS Burnie, while the other sample will be sent to ALS
Perth. ALS Perth will assay all samples received and then complete a DMS trial on the second ore sort reject and
fines samples which may remove 95% of the mass again from the second ore sort reject and fines to produce
another pre-concentrate – the DMS pre-concentrate.
The DMS pre-concentrate will then be sent to ALS Burnie and combined with the second ore sort product to be
trialled in a pilot-scale gravity plant. The pilot-scale gravity plant at ALS Burnie will produce a tin concentrate from
these samples which will be vital in marketing future product from Tallebung to downstream businesses.
This program will be completed over the coming months with results to be reported regularly as the bulk samples
progress through the large program.
6
METALLURGICAL TESTWORK – DMS TRIAL
During 2024, ore sorting testwork completed by TOMRA Ore Sorting solutions demonstrated an exceptional result
using an aggressive ore sorting method where a substantial increase in tin grade with reasonable recovery of tin
was achieved in less than 2% of the original mass. This showed that most of the tin could be recovered while
rejecting 98% of the sorted mass (Table 1).
While this result shows the potential for greater tin pre-concentration upgrade and mass reduction from TOMRA
ore sorting, the payoff between upgrade and tin recovery requires further optimisation to be completed in the
ongoing bulk sampling program.
Table 1: Results for the TOMRA ore sorting testwork. Silver (Ag) shows a strong upgrade and reasonable
recovery with the tin (Sn) in the sorted products, however tungsten (W) appears to be largely upgraded in the
‘Fines’ fraction. NB: The ‘High Recovery’ product includes the ‘High Upgrade’ sorted sample.
Sn
Grade
%
Sample
Head Sample
before sorting
8-32mm High
Upgrade Sort
8-32mm High
Recovery Sort
8-32mm 1st
Sorting Waste
<8mm Fines
(unsorted)
Sn
Sn
Recovery Upgrade
%
x
Ag
Grade
g/t
Ag
Ag
Recovery Upgrade
g/t
x
W
Grade
%
W
Recovery
%
0.10
100
-
10.7
100
-
0.45
100
4.42
82.9
43.9
342
55.3
29.3
0.01
0.0
0.65
91.5
6.4
57.2
76.0
6.4
0.01
0.2
0.01
8.5
0.1
3.0
8.5
0.1
0.07
11.0
0.14
-
-
8.0
-
-
2.04
88.7
To investigate better tin recovery processes with the aggressive ore sorting, a successful DMS trial was
completed. This was aimed at providing a solution to recover the tin lost in the aggressive ore sorting process
while still substantially reducing the mass for further processing. Results are detailed in Table 2 for this testwork
and show 75% of the tin lost in the aggressive ore sorting process can be recovered in 5.7% of the original waste
mass in a 1.50% Sn pre-concentrate, rejecting over 94% of the waste mass.
Table 2: Results for DMS testwork to recover tin from the TOMRA ore sorting testwork. Silver (Ag) again shows a
strong upgrade and recovery with the tin (Sn) with poor recovery of tungsten (W).
Sample
8-32mm
Sorting
Waste
DMS
Product
DMS
Waste
%
Sn
Grade
%
Sn
Recovery
%
Sn
Upgrade
x
Ag
Grade
g/t
Ag
Recovery
g/t
Ag
Upgrade
x
W
Grade
%
W
Recovery
%
100
0.11
100
-
19
100
-
0.12
100
5.7
1.50
74.5
13.6
167
50.0
8.8
0.33
15.3
94.3
0.03
25.5
0.3
9.3
50.0
0.5
0.11
84.7
Mass
This result represents an excellent solution to recovering the tin lost during the aggressive ore sorting process
while still maintaining a large +90% mass rejection of the total feed. This will be further reviewed and optimised in
the upcoming bulk sampling and metallurgical testwork over the coming months.
7
In addition to delivering a much higher tin grade, the benefits of ore sorting and mass reduction include:
•
Reduced CapEx as only a fraction of the sorted mass requires processing and therefore a significantly
smaller and lower cost processing plant can be considered to support any future mining operation;
•
Reduced Opex through reduced mill throughput, lower processing costs and lower cost bulk-mining
techniques;
•
Excellent environmental outcomes including:
–
A small fraction of the water will be required to produce saleable tin concentrates;
–
A small fraction of the power will be required to produce saleable tin concentrates; and
–
Reduced mine footprint including smaller waste emplacements such as tailings dams.
This sample was from drill-hole TBD012 between 42-92m of PQ half core for a total of 289.2kg which was sent to
TOMRA Ore Sorting Solutions test facility in Castle Hill, Sydney, NSW in July last year. The sample was crushed
to -40mm and sized with -8mm fraction retained separately as a fines sample. The 8-32mm sample was then sorted
via XRT ore sorting to obtain a high tin recovery sorting setting.
The product (tin-bearing) fraction was then sorted again for a high tin upgrade sort, with the goal of recovering as
much tin as possible in as little mass as possible. The waste from this second sort is what has been trialled in the
DMS testwork program, the results of which are detailed above.
ENVIRONMENTAL STUDIES AND MINING APPROVALS
Environmental studies required to secure key mining approvals continue to be expedited, with an initial
background biodiversity study completed and a weather station being completed over the last quarters.
The installation of a weather station will provide vital data for the environmental studies needed for the mining
approvals process. This installation complements the work already completed on these studies, with the
groundwater monitoring bores already installed and geochemical studies well advanced.
The installation of these data collectors and the biodiversity and geochemical studies are all in preparation to
quickly advance the mining approvals process required to commence development of the Tallebung Tin Project.
NEXT STEPS
The major Reverse Circulation (RC) drilling program outlined above will be progressed throughout the June
Quarter, comprising at least 70 RC drill-holes for a total of approximately 8,000m. The current program will target
further shallow extensions to the tin mineralisation, aiming to further broaden the Tallebung Deposit. First assay
results are anticipated in May, with a steady stream of results expected over the coming months as drilling
continues.
In parallel, SKY is advancing the bulk sample metallurgical program to optimise the process flowsheet and produce
marketable tin concentrates to aid in offtake marketing.
The new drilling results and bulk sampling data will support the delivery of an updated Mineral Resource Estimate
(MRE) for Tallebung. The new MRE and metallurgical work will then be incorporated into Mining Studies to
demonstrate the potential Tallebung project economics.
8
NARRIAH PROJECT (EL 9524, SKY 100%)
MAIDEN DIAMOND DRILLING PROGRAM
During the March Quarter 2024, compilation of historic data showed strong potential for near surface tin-tungsten
mineralisation at the Conapaira Mining Reserve. This was further evidenced by the extensive historic workings in
the area.
A site visit for ground-truthing historic data, geological mapping and rock chip sampling was completed in the and
discovered extensive workings throughout the mining reserve and widespread evidence for these workings
occurring in close, prospective proximity to the Erigolia Granite Margin. Evidence for the close proximately to the
granite margin included exposed and preserved roof pendants.
Given the prospective position of these historic workings, rock chip samples were taken of areas of outcrop and
mine workings. These rock chip samples successfully identified high-grade tin, tungsten and silver mineralisation
over a strike length of more than 3km, with results including:
•
•
•
1.80% tin, 13.9g/t silver & 0.05% copper (JN240223-05);
1.50% tin, 0.26% tungsten & 14.7g/t silver (JN240223-04);
1.20% tin & 1.77% tungsten (JN240223-10).
GEOPHYSICAL MAGNETICS SURVEY
In the September Quarter, FY2025, a large aeromagnetics survey was flown over the +16km long prospective
horizon within the Narriah Project. The results from this survey will be combined with the rock chip results from
the Conapaira Mining Reserve to aid in targeting large-scale and high-grade tin and tungsten mineralisation.
Furthermore, the potential hard rock tin mineralisation in the majority of the Narriah Project remains untested by
previous explorers.
The results of the geophysical survey will be combined with the thorough compilation of the historic data and the
rock chip results to target follow up drilling, aiming to discover a large-scale and high-grade tin-tungsten deposit.
DORADILLA PROJECT (EL 6258, SKY 100%)
POLYMETALLIC MINERALISATION – METALLURGICAL TESTWORK PROGRAM
A recent review of historic petrology and metallurgical testwork at the Doradilla Tin Deposit identified that the tin
is hosted in fine cassiterite in the vicinity of the Doradilla Tin Target on the south-west end of the ‘DMK’ Line.
Additionally, this mineralisation has not been tested for concentration via modern flotation methods.
This represents an encouraging development at Doradilla. Work is underway to confirm the historic findings and,
if confirmed, to test modern flotation methods to concentrate the tin. This work will aim to evaluate if it is possible
to produce a saleable tin concentrate using these methods on the Doradilla mineralisation and, subsequently, if
there are viable pathways to mine economically at Doradilla.
SKY is continuing to work with engaged metallurgical consultants, UNSW, ALS Burnie and ANSTO, along with
other experts, to continue to develop the broad range of methods available to extract the REE, tin and polymetallic
mineralisation on the DMK Line to unlock the high-value, widespread mineralisation discovered at Doradilla.
This work will include ongoing data compilations, targeted geophysical surveys as required and continuing
geological studies by SKY in partnership with UNSW.
9
CULLARIN PROJECT: GOLD-LEAD-ZINC-COPPER (EL 7954, SKY 80%; DVP JV)
HUME TARGET – DIAMOND DRILLING AND DHEM
Diamond drilling completed at the Hume Target in 2021 highlighted the potential of the high-grade, gold-lead-zinccopper mineralisation at depth at Hume. HUD031 intercepted intervals of massive sulphides and strong base metal
mineralisation, deeper than any previous drilling at Hume. Results included:
HUD031:
32m @ 5.09% Pb+Zn, 0.15% Cu, 6g/t Ag from 420m including;
6m @ 8.93% Pb+Zn, 0.51% Cu, 18g/t Ag, 0.13g/t Au from 446m
SKY was encouraged by these thicker intervals of mineralisation at the Hume Target. In the March 2023 Quarter,
SKY re-entered HUD030 and extended the hole to intercept the Hume Structure 100m below HUD031. Previously,
HUD030 had been drilled to 303.6m in 2021 to test for extensions to the strong base metal mineralisation intercepted
in HUD005 (6m @ 1.28% Cu & 12.44% Pb+Zn). HUD030 was extended and drilled on to 702.4m.
Geological logging and modelling of HUD030 indicated that the hole had drilled through an interpreted moderately
west-dipping fault named the Eastern Fault. Although the hole intersected multiple zones of intense sericite-silicapyrite alteration, results were subdued. The assay results and advances in the geological understanding of the
Hume Target from this drilling will be studied by SKY geologists to identify any further targets for expanding the
gold-rich, polymetallic mineralisation at the Cullarin Project.
SKY is evaluating a number of new approaches to delineate and target further mineralisation at Cullarin in the
coming quarters. These will aim to highlight prospective areas for discovering more of the high-grade
mineralisation already encountered across the project.
IRON DUKE PROJECT: COPPER-GOLD (EL6064 & 9191, SKY 100%)
100% SKY (EL6064 & 9191)
SKY exercised the option to purchase EL6064 – Iron Duke Project and SKY now holds 100% of the Project. The Iron
Duke Project covers the Iron Duke Shear Zone, which extends over a strike length of at least 4km and remains
open to the south. Several historic copper mines occur along the Iron Duke Shear Zone including the Iron Duke,
Christmas Gift, Monarch, Mount Pleasant and Silver Linings mines, along with several unnamed copper workings
and shafts. In the June 2021 Quarter, SKY completed a maiden drilling program at the Iron Duke Mine, in
conjunction with a VTEM survey and DHEM, to identify extensions to the high-grade copper-gold mineralisation
along the Iron Duke Shear Zone (SKY:ASX Announcement 2nd June 2021).
An RC and diamond drilling program is planned to test for further extensions to the Iron Duke mine and test the
previously undrilled historic mines at the Christmas Gift Workings (comprising of the Christmas Gift, Monarch,
Mount Pleasant and Silver Linings mines). This program was delayed due to extremely wet ground conditions
preventing access to the area. Currently, this program is planned for the following quarters after a detailed review
of the geophysics, mining records, historic data and previous drilling to develop robust targets for further drill
testing and expansion of the known Iron Duke mineralisation.
CALEDONIAN PROJECT: GOLD
100% SKY (EL8920 & EL9020)
SKY has now completed a soil sampling program, a phase of AC drilling, two phases of RC drilling and two diamond
drill holes at the Caledonian Target. A review of both SKY’s and historic results indicates that the Caledonian gold
mineralisation likely represents a shallow, sub-horizontal blanket of oxide and supergene gold mineralisation
developed over an oxidised skarn.
10
SKY completed a shallow aircore (AC) drilling program over the area consisting of 38 vertical AC holes for a total
of 697m on 50-100m spacing over the 600m x 400m area of mineralisation defined by the previous drilling, soil
sampling and costeaning. Due to significant ground waters intersected by the AC drilling, which prevented all but
four of the 38 holes drilled from reaching refusal, SKY does not consider the target concept of a shallow,
subhorizontal blanket of oxide and supergene gold mineralisation to have been effectively tested. These results
will be evaluated, along with the previous drilling, to direct SKY to further shallow high-grade oxide gold
mineralisation in the target area.
SKY has been informed of the proposed development of a solar farm on the northern area of EL8920. This area
covers the Jerrawa Strike, which is a trend of metallic occurrences that SKY interprets to be an exhalative horizon
with strong potential to host gold-silver and base metal mineralisation. SKY is continuing to work with the solar
farm developers to ensure that the solar farm will not be developed over significant mineralisation. The work to
date has delineated a gold soil anomaly which SKY plans to follow up in the following quarters, pending ongoing
negotiations with the Solar Farm developers.
GALWADGERE PROJECT: COPPER-GOLD
100% SKY (EL6320)
SKY and Burrendong Minerals Ltd (BML) entered into to a purchase agreement for the divestment of SKY’s noncore Galwadgere Project. Galwadgere, EL6320, will be purchased outright with $600,000 worth of BML shares on
the successful IPO of BML within a year from the commencement of the agreement.
The Galwadgere Project has been returned to SKY, 100%, at the end of the March Quarter after Burrendong
Minerals failed to list on the ASX with an IPO of a portfolio of nearby projects. SKY will continue to develop value
at Galwadgere with a review of the non-core Galwadgere Project while remaining focused on developing the
Company’s core assets.
KANGIARA PROJECT: GOLD
80% SKY (EL8400 & EL8573; DVP JV)
The Kangiara Project (EL8400, EL8573) is located 30km north-west of Yass in the Southern Tablelands of New South
Wales (Figure 5). The project contains volcanic/volcaniclastic rocks of the Silurian Douro Group, considered
prospective for gold and base metal (copper-zinc) mineralisation. The high-grade Kangiara Mine operated during
the early 1900s, with documented production of ~40,000 tonnes at 16% Pb, 3% Cu, 5% Zn, 280g/t Ag and 2g/t Au
from narrow north-south trending sulphide veins (ASX: PDM 18 June 2009). Previous work by Paradigm Metals led
to the calculation of an Indicated and Inferred Mineral Resource at Kangiara.
Desktop studies have identified potential for copper-gold mineralisation at the Crosby Prospect. Field
investigations are planned for the upcoming quarters to investigate this prospect.
11
CORPORATE
FINANCIAL
During the quarter $667k was spent on the exploration activities outlined in this report.
No mining production and development activities were undertaken for the quarter.
During the quarter $53k was paid as Non-Executive Director fees.
TENEMENT SUMMARY
Table 2: Tenement Summary.
Holder
Tarago Exploration Pty Ltd
(DVP sub)
Ochre Resources Pty Ltd
(DVP sub)
Ochre Resources Pty Ltd
(DVP sub)
Aurum Metals Pty Ltd (SKY
sub)
Aurum Metals Pty Ltd (SKY
sub)
Cuprum Aurum Pty Ltd (SKY
sub)
Balmain Minerals Pty Ltd
(SKY sub)
Balmain Minerals Pty Ltd
(SKY sub)
Stannum Pty Ltd
(SKY sub)
Stannum Pty Ltd
(SKY sub)
Stannum Pty Ltd
(SKY sub)
Stannum Pty Ltd
(SKY sub)
Equity
Licence ID
Grant Date
Expiry Date
Units
Area
Comment
Cullarin Project, SKY:
DVP JV
Kangiara Project,
SKY: DVP JV
Renewal submitted
Kangiara Project,
SKY: DVP JV
80%
EL7954
19-6-2012
19-6-2028
51
144 km2
80%
EL8400
20-10-2015
20-10-2024
52
147 km2
80%
EL8573
23-5-2017
23-5-2029
17
48 km2
100%
EL8920
5-12-2019
5-12-2025
65
183 km2
Caledonian Project
100%
EL9120
30-3-2021
30-3-2027
50
141 km2
Caledonian Project
Galwadgere Project
- agreement with preIPO Burrendong
Minerals Ltd
100%
EL6320
12-10-2004
12-10-2026
14
41 km2
100%
EL6064
21-3-2003
20-3-2028
5
15 km2
Iron Duke Project
100%
EL9191
8-6-2021
8-6-2027
60
174 km2
Iron Duke Project
100%
EL6258
21-6-2004
21-6-2026
38
113 km2
Doradilla Project
100%
EL6699
10-1-2007
10-1-2027
14
41 km2
Tallebung Project
100%
EL9524
8-2-2023
08-02-2029
92
262 km2
Narriah Project
100%
ELA6786
Applied for
on 5-7-2024
-
101
287 km2
Narriah Project –
Application
This report has been approved for release by the Board of Directors.
For further information:
Investors:
Oliver Davies, CEO – Sky Metals
M: 0430 359 547
Media:
Nicholas Read – Read Corporate
M: 0419 929 046
12
JOIN SKY METALS’ INTERACTIVE INVESTOR HUB
Visit skymetals.com.au to interact with Sky Metals’ announcements and updates
To watch a video summary of this announcement & engage with SKY click here
About the Tallebung Tin Project (100% SKY)
Tallebung stands as an open-pit, technology enabled, near-term tin development project. Tallebung is uniquely
placed to provide secure tin supply, to feed irreplaceable and rapidly expanding tin demand, essential in semiconductors, electronics and solar PV technologies.
The Tallebung Tin Project is located at the site of large-scale historical tin mining in central Western NSW