Tallebung Key NSW Approvals Milestone Achieved
Released
Released
Announcement PDF
ASX: SKY
ASX ANNOUNCEMENT
3 June 2026
SKY METALS LIMITED
+61 2 6360 1587 2 HAWTHORN PLACE, ORANGE NSW 2800 WWW.SKYMETALS.COM.AU ABN 46 098 952 035
Watch a video summary of this announcement & engage with SKY here
TALLEBUNG MOVES CLOSER TO DEVELOPMENT FOLLOWING KEY NSW
APPROVALS MILESTONE
• Major approvals milestone achieved for the Tallebung Tin-Silver-Tungsten Project, with the
NSW Department of Planning, Housing and Infrastructure issuing the Planning Secretary’s
Environmental Assessment Requirements (SEARs).
• Issuance of SEARs formally advances the Tallebung Project into the Environmental Impact
Statement (EIS) phase of the NSW State Significant Development (SSD) process, marking
another critical step toward development approval.
• Progression toward EIS submission represents a key de‑risking milestone, integrating SKY’s
extensive existing studies into a comprehensive environmental, technical and approvals
framework to advance Tallebung toward development.
• Updated Mineral Resource Estimate (MRE) and Pre‑Feasibility Study (PFS) on track for
release in the coming weeks, representing major upcoming catalysts.
• The updated MRE will incorporate multiple new shallow, broad and high‑grade
tin‑tungsten‑silver intercepts, reinforcing the scale and quality of the central resource and
supporting early development potential. Recent results to be incorporated include:
TBRC395: 23m @ 1.14% tin & 0.03% tungsten from 19m, including:
- 6m @ 2.72% tin & 0.06% tungsten from 19m
TBRC410: 17m @ 0.79% tin & 0.04% tungsten from 47m, including:
- 4m @ 2.27% tin & 0.02% tungsten from 50m
TBRC218: 6m @ 1.32% tungsten, 20.2g/t silver & 0.10% tin from 21m, and:
10m @ 0.60% tungsten, 80.6g/t silver & 0.0.10% tin from 51m
• Additional assays from extensional drilling pending, with potential to support continued
future resource growth and expansion outside the pending MRE update.
SKY Managing Director & CEO Oliver Davies commented: “The receipt of SEARs is a key milestone for Tallebung
and marks another important step in advancing the project towards development. Progressing into the EIS phase
provides a clear and structured pathway through the NSW approvals process and reflects the substantial work
completed across environmental studies, technical assessments and stakeholder engagement. With an updated
Mineral Resource and Pre‑Feasibility Study imminent, we are entering an exciting period for SKY as Tallebung
continues to advance on multiple fronts simultaneously, with approvals, resource growth and development studies
converging to support its emergence as a potential near-term Australian tin-silver-tungsten producer.“
2
Figure 1: Planned development and approvals timeline for the Tallebung Project.
Sky Metals Limited (ASX: SKY) (“Sky Metals” or the “Company”) is pleased to advise that its 100%-owned
Tallebung Tin-Silver-Tungsten Project in NSW has achieved a significant development milestone, with the NSW
Department of Planning, Housing and Infrastructure issuing Planning Secretary’s Environmental Assessment
Requirements (SEARs) following its successful review of the Project’s Scoping Report.
The issuance of the SEARs formally advances Tallebung into the Environmental Impact Statement (EIS) phase of
the NSW State Significant Development (SSD) approvals process.
TALLEBUNG PROJECT (EL 6699, SKY 100%)
ACCELERATING APPROVALS PROGRESS
The successful review of the Tallebung Scoping Report and issuance of the Planning Secretary’s Environmental
Assessment Requirements (SEARs) represents a major milestone, marking the transition from early-stage
approvals into the detailed assessment phase required for development consent. This progression provides a clear
and structured pathway forward as Sky Metals commences preparation of the EIS.
Importantly, the Company has already completed a substantial body of baseline environmental studies, technical
assessments and stakeholder engagement activities, positioning Tallebung for efficient advancement through the
EIS phase.
This early work includes environmental surveys, site assessments and initial approvals planning, enabling key
inputs to be rapidly integrated into the EIS as part of a coordinated and streamlined approvals strategy.
In parallel with approvals progression, Sky Metals continues to strengthen the underlying resource base, with
recent drilling delivering shallow, broad, high‑grade tin‑tungsten‑silver intercepts within the central portion of the
deposit. These results are expected to form a key component of the early mine life production profile, supporting
rapid access to higher‑grade mineralisation from surface and enhancing project economics.
3
The Company has completed it’s major drilling campaign that commenced in 2025, with more than 500 drill holes
and assays results received for over 500 holes which will form the MRE update.
The Company is entering a period of strong news flow, with an updated Mineral Resource Estimate (MRE) and
Pre‑Feasibility Study (PFS) on track for release in the coming weeks, incorporating all results from the recent
growth drilling program.
This announcement is authorised for release by the Board of Sky Metals Limited.
Investors:
Oliver Davies – Managing Director & CEO
+61 (0) 430 359 547
Media:
Nicholas Read – Read Corporate
+61 (0) 419 929 046
JOIN SKY METALS’ INTERACTIVE INVESTOR HUB
Visit skymetals.com.au to interact with Sky Metals’ announcements and updates
To watch a video summary of this announcement & engage with SKY click here
About the Tallebung Tin Project (100% SKY)
Tallebung stands as an open-pit, technology enabled, near-term tin development project. Tallebung is uniquely
placed to provide secure tin supply, to feed irreplaceable and rapidly expanding tin demand, essential in semi-
conductors, electronics and solar PV technologies.
The Tallebung Tin Project is located at the site of large-scale historical tin mining in central Western NSW
where tin was first discovered in the 1890s. SKY is progressively defining a large-scale hardrock tin resource
with recent higher-grade tin zones discovered on the margins of the known deposit and exceptional
metallurgical performance demonstrated across the entire known deposit.
The shallow, open-pit tin veins combined with the ideal nature of the tin, hosted as large, discrete grains of
simple tin-oxide (cassiterite minerals), all ideally lends itself to low-cost tin production advantages, including
exceptional X-ray based ore sorting performance, demonstrated to upgrade the tin up to 44x, prior to low-cost
gravity separation to produce a saleable tin concentrate.
4
Previously Reported Information
The information in this report that references previously reported exploration results is extracted from the
Company’s ASX market announcements released on the date noted in the body of the text where that reference
appears. The previous market announcements are available to view on the Company's website or on the ASX
website (www.asx.com.au). The Company confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcements. The Company confirms that the
form and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcements.
Disclaimer
This report contains certain forward-looking statements and forecasts, including possible or assumed reserves
and resources, production levels and rates, costs, prices, future performance or potential growth of Sky Metals
Ltd, industry growth or other trend projections. Such statements are not a guarantee of future performance and
involve unknown risks and uncertainties, as well as other factors which are beyond the control of Sky Metals Ltd.
Actual results and developments may differ materially from those expressed or implied by these forward-looking
statements depending on a variety of factors. Nothing in this report should be construed as either an offer to sell
or a solicitation of an offer to buy or sell securities.
This document has been prepared in accordance with the requirements of Australian securities laws, which may
differ from the requirements of United States and other country securities laws. Unless otherwise indicated, all
ore reserve and mineral resource estimates included or incorporated by reference in this document have been,
and will be, prepared in accordance with the JORC classification system of the Australasian Institute of Mining,
and Metallurgy and Australian Institute of Geoscientists.